On this page
6 min read

Sydney light rail construction only months away

Construction on Sydney’s light rail begins in less than four months with a plan established for minimal disruption to commuters, motorists and businesses.

Light rail will transform the city with fast, reliable journeys from Circular Quay through the CBD to south east Sydney’s sporting and entertainment precincts, medical facilities, education and business areas.

Major construction begins at Moore Park in September 2015, with construction beginning on George Street between King and Market Streets beginning October 23.

Reducing the impact of construction

Measures to help reduce the impact of construction work include:

• Staggered construction on a ‘get in, get out’ basis to minimise disruption to businesses and residents.

• Staged construction across 31 zones with no one zone affected for the entire period.

• Individual CBD construction zones will be impacted for between eight and 13 months before being handed back for public use.

Assisting bus commuters

The closure of George Street to buses means customers’ stops will move to other bus corridors including Elizabeth Street, Castlereagh Street, Park Street, Druitt Street, Clarence Street and York Street.

The introduction of a new bus timetable on 4 October will provide bus commuters plenty of time to familiarise themselves with the new timetable before it is implemented.

Keeping Sydney moving

Minister for Roads, Maritime and Freight Duncan Gay said the government was throwing everything into alleviating pressure.

“We’re appointing a central body, putting work on hold where we can carry out supporting road upgrades before construction starts,” Mr Gay said.
“We know this is going to be a difficult period of change but we’re Sydney and we’re used to rising to the challenge – I know light rail will be no exception.”

Key major construction dates

Major construction means excavation works, rebuilding roads and laying tracks. Work will continue on technical fit out and the construction of individual platforms after this time but will be confined to narrower corridors and will be significantly less intrusive.

Pedestrian access will be maintained throughout construction as will local vehicle and emergency vehicle access. East-West crossings of the CBD will also be maintained.

Key dates

  • September 2015, construction access for Moore Park West Corridor
  • October 2015, CBD works start
  • January 2016 start of Randwick branch
  • February 2016, start of Kingsford branch
  • August 2016 start of work in Surry Hills
  • September 2016, completion of the first pedestrian zone block in George Street
  • May 2017 completion of final pedestrian zone block in George Street
  • September 2017, start of the final work zone along the route (Elizabeth St to Chalmers St)
  • September 2017, arrival of light rail vehicles
  • April 2018, completion of major civil construction; ongoing works continue to finalise the installation of electronic systems and construction of platforms
  • June 2018, testing commences

Source: News Release, New South Wales Government, 28 May, 2015

https://www.youtube.com/watch?v=h3h2WiwoVaU

Start Your Journey

Take the first step towards better results. Book your expert consultation today!

More articles

Contact us
All
Employment Enquiry
All
All
.docx,.rtf,.doc,.pdf fiel extensions are only allowed.
.docx,.rtf,.doc,.pdf fiel extensions are only allowed.